One of the first questions every homeowner asks: how long is this going to take? Here's the realistic timeline for each exterior project from first phone call to final walkthrough.
Window Replacement
Consultation to install: 3-6 weeks (custom manufacturing takes 2-4 weeks after ordering)
Installation time: Most homes with 10-15 windows are completed in 1-2 days. Larger projects (20+ windows) may take 2-3 days. Each window opening is exposed for only minutes during the swap — your home is never left open overnight.
Learn about our window process →
Roof Replacement
Consultation to install: 1-3 weeks for retail projects. Insurance claim roofs add 2-4 weeks for the claim process.
Installation time: Small ranch (15-20 squares): 1 day. Average 2-story (20-30 squares): 1-2 days. Large or complex: 2-3 days. Weather delays are possible during spring storm season.
Detailed roof replacement timeline →
Siding Replacement
Consultation to install: 2-4 weeks depending on material availability.
Installation time: Most homes take 1-2 weeks. Siding is the longest exterior project because every square foot of exterior surface must be stripped, inspected, wrapped, and re-clad. Larger homes or those requiring significant sheathing repairs take longer.
Learn about our siding process →
Entry Door Installation
Consultation to install: 2-6 weeks (custom orders take longer than standard sizes).
Installation time: Most entry doors are installed in a single day — typically 4-6 hours. Your home is never left unsecured overnight.
Learn about our door process →
Patio Door Installation
Consultation to install: 3-6 weeks (most patio doors are custom-ordered).
Installation time: Standard sliding or French patio doors: 1 day. Multi-slide systems or projects requiring structural modifications: 1-2 days.
Storm Door Installation
Consultation to install: 1-2 weeks.
Installation time: 1-2 hours. The quickest exterior project with one of the biggest quality-of-life impacts.
Gutter Installation
Consultation to install: 1-2 weeks.
Installation time: Most homes: 1 day. Our seamless gutter machine fabricates each run on-site to exact measurements. Gutter guards add a few hours.
Whole-House Exterior Renovation
Consultation to install: 4-8 weeks (coordinating materials for all trades).
Installation time: 2-4 weeks total, done in sequence: roof first, then windows and doors, then siding, then gutters last. Why order matters →
Speed Up Your Timeline
The biggest delay in most projects is decision-making, not installation. Once you've selected your products and signed off on the estimate, we move quickly. Call (331) 250-3726 to start your free consultation today.